Justia Wyoming Supreme Court Opinion Summaries

Articles Posted in Construction Law
by
Russ and Debi Ropken hired a construction company to build a custom home based on an oral agreement. The contractor began work and sent invoices for services and materials, which the Ropkens paid until May 2022, after which they stopped making payments. In July 2022, the Ropkens removed the contractor from the site. The contractor then sent a demand letter for three unpaid invoices totaling $276,169, but the Ropkens refused to pay. The contractor sued to recover the unpaid amount.In the District Court of Park County, the Ropkens admitted owing at least $176,870.21. At the conclusion of a jury trial, the jury found there was a valid contract, the Ropkens had breached it, and awarded the contractor $258,587.70 in damages. The district court entered judgment for that amount and permitted the contractor to request prejudgment interest. The contractor timely filed for prejudgment interest, and the Ropkens objected. The district court found for the contractor, awarding $33,473.25 in prejudgment interest at a statutory rate, and calculated interest from the date of the demand letter. The Ropkens paid the judgment but appealed the prejudgment interest award.The Supreme Court of Wyoming reviewed whether the district court erred in awarding prejudgment interest and whether due process was violated by granting interest without an evidentiary hearing. The court held that a district court may award prejudgment interest even when it is not the trier of fact, as prejudgment interest is a matter of law and not fact. The court found the claim was liquidated and the Ropkens had notice. The court also held that the Ropkens received adequate notice and opportunity to be heard, satisfying due process. The Supreme Court of Wyoming affirmed the award of prejudgment interest. View "Ropken v. Yj Construction, Inc." on Justia Law

by
Eiden Construction, LLC (Eiden) entered into a subcontract with Hogan & Associates Builders, LLC (Hogan) for earthwork and utilities on a school construction project. Hogan sued Eiden and its bonding company, AMCO Insurance Company (AMCO), for breach of contract, claiming Eiden failed to complete its work, including draining sewage lagoons and constructing a fire pond. Eiden counterclaimed for unpaid work, arguing it was not responsible for draining the lagoons and that Hogan did not comply with the subcontract’s notice and opportunity to cure provisions. AMCO argued it was not liable under the performance bond because Eiden did not breach the subcontract and Hogan did not provide proper notice.The District Court of Uinta County found for Hogan on the claim regarding the sewage lagoons but not on other claims, ruling AMCO was not liable under the bond due to lack of notice. Eiden and Hogan both appealed. Eiden argued the court erred in finding it responsible for draining the lagoons and in awarding Hogan damages billed to an associated company. Hogan contended the court erred in not awarding damages for other work and in its calculation of prejudgment interest.The Wyoming Supreme Court affirmed the lower court’s decision. It held Eiden breached the subcontract by not draining the lagoons and that Hogan was entitled to recover costs for supplementing Eiden’s work. The court found Eiden’s late completion of the septic system justified Hogan’s directive to expedite lagoon drainage. It also ruled Hogan properly paid the supplemental contractors, despite invoices being sent to an associated company. The court rejected Hogan’s claims for additional damages, concluding Eiden complied with the notice to cure provisions for the fire pond and other work. The court also upheld the lower court’s calculation of prejudgment interest, applying the offset before calculating interest. View "Hogan & Associates Builders, LLC v. Eiden Construction, LLC" on Justia Law

by
Summit Construction filed a lawsuit against Jay Koontz and Jennie L. Kennette for breach of contract and unjust enrichment, alleging nonpayment for work performed on Mr. Koontz’s home based on an oral agreement. The work included an addition to the home and extensive renovations to the existing structure. The District Court rejected both claims, determining that there was no enforceable oral contract between the parties and that Summit did not sufficiently prove its damages for the unjust enrichment claim.The District Court found that the parties had not mutually agreed to sufficiently definite terms for an oral contract. The court noted that the project progressed without a clear understanding of the scope of work, how it would be paid for, and who would be responsible for payment. The court also found that Summit's invoices did not clearly define the terms of the contract. Furthermore, the court concluded that Summit had failed to prove the amount by which Mr. Koontz was unjustly enriched, i.e., its damages.Upon appeal, the Supreme Court of Wyoming affirmed the District Court's decision. The Supreme Court agreed that Summit had failed to show the existence of an enforceable oral contract with either Mr. Koontz or Ms. Kennette. The court also agreed with the lower court's finding that Summit had failed to establish its damages to a reasonable degree of certainty, which is necessary for an unjust enrichment claim. View "Summit Construction v. Koontz" on Justia Law

by
The Supreme Court reversed in part and affirmed in part the order of the district court granting summary judgment in favor of Ghidorzi Construction Company, LLC and dismissing the complaint brought by Primrose Retirement Communities, LLC and Gillette Retirement, LLC its local affiliate (together, Primrose), holding that the district court erred in granting summary judgment on Primrose's breach of contract claim.Primrose filed a complaint against Ghidorzi alleging negligence, breach of contract, and breach of the implied covenant of good faith and fair dealing. The district court granted summary judgment in favor of Ghidorzi following a hearing. The Supreme Court reversed in part, holding (1) there were material questions of fact precluding summary judgment on the interpretation of the contract and whether Ghidorzi's actions contributed to Primrose's damages; and (2) the district court properly concluded that the contract language obviated any need to impose an implied covenant. View "Primrose Retirement Communities, LLC v. Ghidorzi Construction Co." on Justia Law

by
In this breach of contract and breach of warranty case the Supreme Court affirmed the judgment of the district court granting Shelly Besel's motion for summary judgment and dismissing Shelly from the litigation with prejudice, holding that Shelly was properly dismissed from the litigation.Appellants hired Leonard Besel to remodel their home. Prior to completing the project Leonard terminated the contract. Appellants brought this action naming Shelly as a defendant and alleging that Shelly was a partner of her husband's contracting business. Shelly moved to dismiss herself from the lawsuit, disavowing any partnership interest in her husband's business. The district court granted Shelly's motion. The Supreme Court affirmed, holding that no material issue of fact existed based on the evidence as to Shelly's status vis a vis the business, and therefore, the record supported the district court's ruling dismissing Shelly from the litigation. View "Norris v. Besel" on Justia Law

by
The Supreme Court affirmed Appellant’s conviction of one count of sexual assault in the first degree, holding that Appellant’s trial counsel did not provide ineffective assistance.The jury in this case concluded that Appellant committed sexual intrusion upon a non-consenting victim whom Appellant knew or had reason to believe was physically helpless. On appeal, Appellant argued that his trial counsel provided ineffective assistance by failing to object to inadmissible evidence, failing to adequately advance her theory of the case, and failing to suppress the statements made by Appellant when under investigative detention. The Supreme Court disagreed, holding that trial counsel was not ineffective in her representation of Appellant. View "Bruckner v. State" on Justia Law

by
Appellant entered into a lease with a Mall to operate a restaurant. The lease required Mall to pay Appellant a finish allowance when certain provisions had been satisfied. The condition at the heart of this dispute required Appellant to provide the Mall evidence that any liens had been satisfied or waived and that “all work has been paid for” before the finish allowance became due. Appellant hired a general contractor to renovate the space. Appellant paid the general contractor in full, but the general contractor did not pay all of the subcontractors. When the Mall did not pay the finish allowance, Appellant filed this lawsuit alleging, inter alia, breach of contract. The district court granted summary judgment in favor of the Mall. The Supreme Court affirmed, holding that the unambiguous terms of the lease required evidence that the general contractor and subcontractors had been paid in full before the Mall was obligated to pay the finish allowance. View "P & N Investments, LLC v. Frontier Mall Associates, LP" on Justia Law

by
Contractor Anderson Carpentry and Construction built a home for Shad and Trisha Bates. Anderson contracted with Century Lumber Center to purchase supplies and materials to build the Bates home. The Bates paid Anderson for materials used on the home, but those funds were applied to other accounts, and the account with Century on the Bates job became delinquent. Century filed a material lien against the Bates property and filed a complaint seeking to foreclose the lien against the property. The district court ultimately enforced the lien. The Supreme Court reversed, holding that the lien was not timely filed as a matter of law. View "Bates v. Chicago Lumber Co. of Omaha" on Justia Law

by
Leon and Brenda Rogers purchased a home from Jeffrey Wright. The Rogers subsequently discovered several defects in the home and sued Wright, JWright Development, LLC, and JWright Companies, Inc. (collectively, the JWright defendants), alleging breach of contract, negligence, breach of warranty, and negligent and intentional misrepresentation. The district court granted summary judgment in favor of the JWright defendants. The Supreme Court reversed the district court’s order on the negligence claim but otherwise affirmed, holding (1) issues of material fact existed regarding whether the builder of the Rogers’ home breached its legal duty to build the home in a reasonable and workmanlike manner; and (2) the district court properly granted summary judgment in favor of the JWright defendants on the remainder of the Rogers’ claims. View "Rogers v. Wright" on Justia Law

by
Electrical Wholesale Supply Co. (EWS) filed this action seeking payment for electrical materials it supplied to a commercial building remodel. EWS sued, among other defendants, Alane Fraser, the owner of the commercial property, and M.J. Bishop Concrete & Construction, Inc. (Bishop Construction), the general contractor, for foreclosure of a construction lien, breach of contract, unjust enrichment, and third party beneficiary. The circuit court denied EWS’s claims. The district court affirmed. The Supreme Court affirmed in part, reversed in part, and remanded, holding that the circuit court (1) applied the wrong statute to the lien notice issue and erred by granting summary judgment in favor of Fraser on the lien claim; but (2) did not err in concluding that EWS did not prove its unjust enrichment claim against Fraser and Bishop Construction. View "Elec. Wholesale Supply Co., Inc. v. Fraser" on Justia Law